July 28th – July 31st 2014

Posted on: August 11th, 2014 by admin (No Comments)

In the period between July 28th – July 31st 2014, kick off meetings were held in Zenica, the companies STEAG, SEPCO III and KTG were present at the meeting to discuss open technical issues regarding the Zenica CHPP project.

July 14th 2014

Posted on: August 11th, 2014 by admin (No Comments)

On July 14th 2014, KTG Zenica obtained the Urban Permit for the Temporary – usage Site during the CHPP construction.

July 4th 2014

Posted on: August 11th, 2014 by admin (No Comments)

On July 4th 2014, KTG Zenica signed a Long Term Gas Supply Agreement with the company MET International AG (Mol Energy Trading International).

June 17th 2014

Posted on: August 11th, 2014 by admin (No Comments)

On June 17th 2014, KTG Zenica submitted the necessary documentation and the requests for the issuance of the Urban permit for the Water Intake from river Bosna.

May 27th 2014

Posted on: August 11th, 2014 by admin (No Comments)

On May 27th 2014, KTG Zenica signed a Long Term Service Agreement with  General Electric for the maintenance of the 9E gas turbines for the duration of 15 years..

1

May 9th 2014

Posted on: August 11th, 2014 by admin (No Comments)

On May 9th 2014 , SEPCO III and its subcontractor Geosonda Ltd Zenica successfully completed the I Phase of the Mission G21.
Mission G21 includes geotechnical investigation of the CHPP site and is mandatory document when requesting the issuance of the Construction Permit.

April 28th 2014

Posted on: August 11th, 2014 by admin (No Comments)

On April 28th 2014, SEPCO III and Energoinvest signed a contract for the CHPP Main Design nostrification/validation and review and for consultancy services during the CHPP Main Design development.