Environmental Impact Assessment

Posted on: December 1st, 2011 by admin (No Comments)

Based on planned installed capacity of 240 MW, the Environmental Impact Assessment (EIA) has been completed in January 2010. The corresponding environmental permit has been issued on March 18, 2010. Due to the increase of the installed capacity from 240 MW to 390 MW, the EIA had to be revised. The revision has been completed in December 2011 and the revised Environmental Permit was released by the Federal Ministry of Environment and Tourism on 24th November 2011.